The new Sunset Clauses Law
passes its first test

Property developers will need to think twice before
rescinding off the plan contracts using a sunset clause,
following the first NSW Supreme Court decision under the new
Conveyancing Amendment (Sunset Clauses) Act 2015 (the Sunset
Clauses Law).
The decision is Jobema Developments Pty Limited v Zhu &
Ors [2016] NSWSC 3.
Justice Black refused to allow Jobema Developments to
rescind Mr Wu’s off the plan contract after the sunset date
had passed, despite the fact that registration of the strata
plan had not taken place prior to the sunset date.
The background
Mr Wu entered into the contract on 6 December 2013, to
purchase a home unit off the plan. It was in a 14 storey
property development project for 72 residential units and 7
commercial lots in Dora Street, Hurstville.
The sunset date for the registration of the Strata Plan
was 31 December 2015. After that date, either party had 14
days to rescind. The vendor’s right to rescind was qualified
by the requirement to ‘use all reasonable endeavours to have
the Strata Plan registered by the sunset date’.
The vendor, Xycom, carried out little construction work
after entering into the contract, although it had DA
approval, possibly because it did not have construction
finance.
In October 2014, Xycom sold the development site (with
the DA) to Jobema Developments. The sale was settled in
January 2015. The sale was subject to the existing off the
plan sale contracts, which were novated to Jobema. Mr Wu’s
contract was one of many novated, but in Mr Wu’s case, the
sunset date was not extended, as was done with some other
contracts.
Jobema started demolition and construction work on 5
February 2015. By December 2015 work was progressing well -
it had constructed 4 out of 5 basement levels. An April 2017
completion was estimated (subject to inclement weather), and
a July 2017 date was estimated for registration of the
strata plan.
Before the sunset date expired, Jobema approached Mr Wu
and other purchasers offering to extend the sunset date in
return for agreeing to a new price (a price increase on
account increased construction costs). Mr Wu did not accept
this offer.
On 1 December 2015, Jobema served Mr Wu (and others) with
a Notice of Intent to rescind the off the plan contract
after 28 days. The Notice set out (1) why it was proposing
to rescind the contract, and (2) the reason for the delay in
creating the strata lot, as required by s 66ZL(4) of the
Conveyancing Act 1919.
The Notice was ‘timed’ to expire so as to enable Jobema
to obtain the Court’s leave to rescind before the right was
lost – which was 14 days after the expiry of the sunset
date.
Was it just and equitable for
Jobema to be given leave to rescind under s 66ZL of the
Conveyancing Act, 1919?
Mr Wu did not consent to, nor oppose, the leave
application made by Jobema. Procedurally, being a leave
application, the Court must still determine whether or not
the requirements of s 66ZL are satisfied.
Section 66ZL(6) requires the developer to satisfy the
Court that it is just and equitable to rescind.
Section 66ZL(7) requires the Court to take into account
specific factors. The Court’s analysis was:
66ZL(7)(a) - the terms of the off the plan contract – Jobema argued it was not responsible for Xycom’s failure to
use its best endeavours to construct the building so that
the Strata Plan could be registered by the sunset date. The
court did not agree. It said that Jobema was responsible for
Xycom’s breach of the best endeavours covenant because it
had knowledge of the lack of progress by Xycom when it
assumed Xycom’s obligations under the sale contracts.
66ZL(7)(b) - whether the vendor has acted unreasonably or
in bad faith – none in this case.
66ZL(7)(c) - the reason for the delay in creating the
subject lot – Jobema cannot shift the blame for the 12 month
delay in construction to Xycom, because it assumed Xycom’s
contractual obligations to the purchasers.
66ZL(7)(d) - the likely date on which the subject lot
will be created – no significance in this case.
66ZL(7)(e) - whether the subject lot has increased in
value – It was suggested that the lot had increased in
value, but no evidence was tendered. The Court stated that a
price increase may ‘have tended against the grant of leave
so as to deprive Mr Wu of his bargain, particularly where
the delay has arisen from Xycom’s apparent failure to
perform obligations which Jobema has now assumed’.
66ZL(7)(f) - the effect of the rescission on each
purchaser – Mr Wu had not consented to the rescission.
66ZL(7)(g) - any other matter that the Court considers to
be relevant – Jobema argued two matters–
- that the increase in construction costs affected the
construction funding. The Court noted that ‘an inability
to rescind’ would not affect the availability of
construction finance – it would only result in a
requirement ‘to contribute additional capital to meet
its lender’s requirements’.
- that the new Sunset Clauses Law was unforeseeable
when it purchased the property. It took effect
afterwards, on 2 November 2015, and so Jobema’s rights
should not be restricted. The Court did not agree –
‘legislative change generally is a foreseeable risk of
business activity’. Specifically - ‘if Jobema assumed
that the legislature would not intervene to increase the
protection available to off the plan purchasers, that
assumption was a business risk’.
The Court was also concerned about – ‘the selective and
unexplained process by which some purchasers had their
sunset dates extended, by agreement with the vendor’ while
other purchasers did not. It said that this ‘is a matter
which tends against the grant of leave sought.’
The Court dismissed the application because it was not
satisfied it was just and equitable.
Comments
Sunset clauses are included in off the plan contracts so
as to limit the property developer’s risk that it might be
locked into an unprofitable contract, forever. The Sunset
Clauses Law does not prohibit sunset clauses, but raises the
hurdle that the property developer must show that the
rescission is just and equitable when the purchaser does not
agree to the rescission.
Jobema’s gamble that it could ignore its predecessor’s
delay and go ahead and rescind the contract has backfired,
because it has now lost the ability to use the sunset clause
at all if it strikes difficulties in the future. In
hindsight, it should have extended the sunset date, for 12
months, to ‘neutralise’ the delay.
The Jobema decision shows that property developers need
to be a bit smarter when considering using a sunset clause
to rescind a contract, so as to be seen to acting justly and
equitably.
For more information on the Sunset Clauses Law, click The
new law for sunset clauses will require property developers
to obtain the buyer’s consent or have a good reason to
rescind a contract.
|